You planned to put solar on the warehouse roof, or add a small wind turbine to cut the power bill. Then July 4, 2026 came and went — and with it, the construction-start grace period for the biggest federal clean-energy credits. If your project did not break ground or lock in costs in time, does that mean the 30% investment credit is gone for good? Not necessarily.
The One Big Beautiful Bill Act (OBBBA), signed July 4, 2025, rewrote the phase-out rules for the technology-neutral credits that replaced the old investment and production tax credits. For wind and solar, the window was intentionally narrow. But there are still two paths to a credit, several alternative technologies that were left untouched, and a late-breaking court decision that restored a safe harbor many developers thought was lost. Here is how the rules work now, and what to do if you missed the first deadline.
How the Deadline Works: Two Clocks, Not One
Under Sections 45Y (clean electricity production credit, or PTC) and 48E (clean electricity investment credit, or ITC), the OBBBA created a two-part test for wind and solar facilities:
Clock 1 — Beginning of construction. Facilities must have begun construction within 12 months of enactment. Because the law was enacted July 4, 2025, that means construction must have begun by July 4, 2026 (the IRS and some court filings refer to July 5, 2026 due to statutory counting — treat July 4 as the safe date).
Clock 2 — Placed in service. Facilities that meet Clock 1 can be placed in service after December 31, 2027 and still qualify, subject to the normal phase-out. Facilities that miss Clock 1 can still qualify only if they are placed in service on or before December 31, 2027.
In plain terms:
- Began construction by July 4, 2026 → you preserved eligibility even if the project is not complete until after 2027.
- Did not begin by July 4, 2026 → you must be fully complete and placed in service by December 31, 2027, or the 45Y/48E credit for that wind or solar facility is not available.
This is a sharp change from pre-OBBBA law, where technology-neutral credits were available for projects beginning construction through 2033 and phasing out only when emissions targets were met.
What "Began Construction" Actually Means
The IRS has long recognized two ways to establish that construction has begun:
-
Physical Work Test — significant physical work of a substantial nature has started. This includes on-site excavation, foundation work, or off-site manufacturing of custom components under a binding contract. Preliminary activities like feasibility studies, permitting, and site clearing generally do not count.
-
Five Percent Safe Harbor — you have paid or incurred at least 5% of the total cost of the facility. For a $400,000 rooftop solar array, that is $20,000 in equipment deposits, binding contracts for inverters and panels, or other includible costs incurred before the deadline. You must then make continuous progress toward completion.
For more than a decade, developers could use either test. That flexibility matters because many small-business projects spend money well before anyone pours concrete.
The IRS Tried to Eliminate the 5% Test — Then a Court Restored It
On August 15, 2025, the Treasury and IRS issued Notice 2025-42, which would have eliminated the 5% Safe Harbor for all wind projects and large solar projects (above 1.5 MW) and left only the Physical Work Test. For small commercial rooftop systems under 1.5 MW, the 5% test would have survived.
That notice followed an executive order directing strict enforcement of the OBBBA termination rules. Developers with financing and procurement in place but little visible construction faced losing eligibility overnight.
On June 6, 2026, the U.S. District Court for the District of Columbia vacated Notice 2025-42 in its entirety and remanded it to the IRS. Multiple law-firm alerts since then confirm the same outcome: the 5% Safe Harbor is back on the table for wind and solar projects that needed to establish beginning of construction by July 4, 2026.
If you wrote off your project because you did not have shovels in the ground by July 4, 2026, pull your invoices again. You may have met the 5% test without realizing it.
Step 1: Audit Whether You Actually Missed the Deadline
Before assuming the credit is lost, run this four-part check with your CPA:
1. Did you pay or incur 5% before July 4, 2026? Gather binding contracts, deposits, and paid invoices for panels, racking, inverters, turbines, or other integral equipment dated on or before July 4, 2026. Equipment that is inventory on a vendor's shelf does not count — it must be custom-manufactured or specifically allocated to your project under a binding contract. Include only costs that are part of the facility's eligible basis.
2. Do you have continuous-progress documentation? The IRS expects continuous efforts after the start date. Keep dated records of permits applied for, interconnection applications, payments to contractors, delivery receipts, and construction logs. A six-month gap with no activity can break continuity unless excused by a recognized disruption.
3. Can you still meet the placed-in-service alternative? Even if you missed the July construction-start date, a project placed in service by December 31, 2027 still qualifies for 45Y or 48E at full value. For a small-business rooftop solar project, 17 months is often enough if equipment is available and permitting is underway. Get a realistic timeline from your installer in writing.
4. Did you satisfy prevailing wage and apprenticeship? Both credits use a dual-rate structure. To claim the full 30% ITC (or the full PTC value), you must pay prevailing wages and employ qualified apprentices for construction, alteration, and repair. Failing the labor rules drops the credit to one-fifth of its value — 6% instead of 30% — which changes the economics dramatically. Document certified payrolls and apprenticeship ratios now, not at tax time.
If the answer to any of these is yes, you may still have a qualifying project. Do not self-disqualify without a professional review.
Step 2: Know Which Credits Are Still Wide Open
The OBBBA was hard on wind and solar but left a surprising number of other technologies untouched through at least 2033:
- Energy storage — standalone batteries paired with solar or charged from the grid still qualify for 48E if construction begins through 2033, with partial credits through 2035.
- Geothermal heat pumps — construction may begin through 2034.
- Nuclear, hydropower, marine and hydrokinetic, qualified fuel cells, and other zero-emissions generation — all remain eligible through 2033 under the same pre-OBBBA phase-out schedule.
- Waste energy recovery property — where it meets the emissions test, it can still qualify.
For a small business, that distinction creates real options. A warehouse owner who missed the solar ITC deadline might still get the full 30% credit on a geothermal heat pump or a battery system designed to shave peak demand. A farm that cannot use wind PTC may still benefit from the Section 45Z clean fuel production credit, which the OBBBA actually extended through 2029 with modifications. Manufacturing businesses should look at Section 45X for eligible components and Section 48C for advanced energy project allocations, though OBBBA froze the 48C pool at $10 billion and eliminated future rounds from revoked certifications.
Bottom line: if your energy goal is lower operating costs and not specifically "solar on the roof," ask your advisor to model an eligible technology that still has runway.
Step 3: Understand What Else Changed Even If You Qualify
Even for projects that met the deadline, several OBBBA changes affect how credits are claimed and monetized:
Foreign Entity Restrictions
The law prohibits claiming Sections 45Y, 48E, and 45X credits if the taxpayer receives material assistance from or has certain ties to prohibited foreign entities — generally entities tied to China, Russia, North Korea, or Iran. The rules apply to taxable years beginning after July 4, 2025 and extend to buyers of transferable credits. Review your supply chain and ownership chart: panels, inverters, or batteries sourced from a prohibited entity can raise the material-assistance cost ratio and disqualify the credit.
Transferability Is Intact but Narrower
Section 6418 still allows 11 clean energy credits to be transferred for cash, but the market is shrinking as fewer wind and solar projects qualify. Buyers must now diligently verify that the underlying credit is still eligible and that neither party is a specified foreign entity. If you planned to sell credits to finance the project, price transfers more conservatively and get a tax opinion.
Direct Pay Survives
Elective pay (often called direct pay) under Section 6417 remains available for tax-exempt organizations, state and local governments, and other eligible entities. Nonprofits that missed the solar window may still use direct pay for an eligible storage or geothermal facility. The amount of the payment follows the underlying credit, so a disqualified wind or solar facility cannot be salvaged through direct pay.
Prevailing Wage, Apprenticeship, Domestic Content, and Energy Community Bonuses
The labor bonus structure, domestic content bonus, and energy community bonus largely survived, with a correction to the 48E domestic content rules and the addition of new nuclear energy communities. These bonuses can add 10 percentage points or more each, but they also add documentation burden. Track them as separate workstreams.
Step 4: Make the Next 17 Months Count
If you missed the July 4, 2026 start and now need to be placed in service by December 31, 2027, treat the next 17 months as a project-management sprint:
Lock the schedule in a contract. Require your installer or EPC contractor to commit to milestones with liquidated damages for delay. Include equipment delivery dates, not just installation dates, because supply-chain slips have pushed many small projects past year-end.
Order long-lead equipment now. Transformers, switchgear, and certain inverters still carry multi-month lead times. A binding contract with a nonrefundable deposit both secures the queue and may help support a 5% Safe Harbor position if the court-restored rule is finalized in your favor.
File interconnection early. Utility interconnection is the most common reason otherwise-ready systems are not placed in service. Submit the application before construction is complete and keep written confirmation of each step.
Separate the facility for credit purposes. If you are building solar plus storage, the storage component may be a separate facility with its own placed-in-service date and its own 2033 window. Structure contracts and invoices to reflect that separation so a missed solar deadline does not drag down an eligible storage credit.
Model the after-credit economics without optimism. Run the return at the 6% base credit as a downside case. If the project only pencils at 30%, identify what must happen to secure the labor bonuses — prevailing-wage payroll, apprenticeship hours — and budget for the compliance cost.
Step 5: Keep Your Books Ready for Scrutiny
The OBBBA preamble and subsequent IRS commentary signal increased examination of clean energy credits. Clean books are not just good practice; they are audit defense.
- Capitalize correctly. The ITC is claimed on the eligible basis of the energy property. Basis includes equipment, installation, and directly related costs, but not land or certain indirect costs. Track basis in a separate fixed-asset subledger, and reduce depreciable basis by 50% of the credit claimed — an error here systematically overstates both the credit and depreciation.
- Track placed-in-service dates by facility, not by invoice. Books often show a single "solar project" spend account. Break out each facility, its 5% Safe Harbor costs, its physical-work costs, and the date it was placed in service and interconnected. An auditor will ask for the facility-level packet, not the general ledger total.
- Reconcile credit sales and direct-pay elections. If you transfer a credit under Section 6418 or elect direct pay under 6417, the cash received is not revenue and the credit is not an expense. Misbooking a $60,000 transfer as income overstates profit and can break a bank covenant. Book it as a reduction of tax or as other income with clear disclosure, consistent with your CPA's guidance.
- Log bonus-credit evidence with the asset. Store prevailing-wage certified payrolls, apprenticeship program registrations, domestic-content mill certificates, and energy-community location evidence alongside the asset record. In a plain-text ledger, that means a transaction comment or linked document for each bonus claimed.
- Watch for recapture. If you claim the ITC and then dispose of the property or change its use within five years, a portion of the credit is recaptured. Maintain a recapture schedule so a future sale does not create a surprise tax bill.
Good records also make it easier to pivot. If solar is no longer the best credit vehicle, your documented spend and timeline may support a storage or geothermal alternative with far less rework.
What to Do This Month
- Pull every energy-related contract and invoice dated June–July 2026 and calculate your 5%-of-total-cost ratio. Share the packet with your tax advisor this week — the vacatur of Notice 2025-42 may have changed your answer.
- Ask your installer for a written placed-in-service-by-December-2027 plan with equipment lead times and interconnection steps. If they cannot commit, get a second bid.
- Price at least one non-solar alternative that still qualifies through 2033. For many small businesses, a battery or geothermal system delivers comparable bill savings with a cleaner credit path.
- Review your supply chain for prohibited-foreign-entity exposure before ordering. A single sourcing choice can cost the entire credit.
- Set up the bookkeeping now. Create a separate chart of accounts or ledger file for the energy facility, log basis and labor documentation as you go, and reconcile monthly so year-end is not a reconstruction exercise.
Missing a tax deadline is frustrating, especially one that was only 12 months long. But the OBBBA did not end clean-energy incentives — it reshuffled them. Projects that begin construction after the window can still qualify by being complete before the end of 2027, projects that spent money before the window may still have met the start test under the restored safe harbor, and a whole set of technologies remains eligible through the next decade. The businesses that benefit will be the ones that audit what they already spent, document what they do next, and keep their books precise enough to survive the closer look the IRS has promised.
Simplify Your Financial Management
Whether you are racing to place a solar facility in service by December 2027 or pivoting to storage or geothermal with a longer runway, the difference between a claimed credit and a kept credit is documentation. Tracking basis, bonus eligibility, and placed-in-service dates in a transparent, auditable ledger pays for itself the first time an examiner asks for the facility packet. Beancount.io offers plain-text, version-controlled accounting that keeps every energy investment — and every credit — fully traceable. Get started for free and bring the same rigor to your books that the new rules demand of your projects.